In Project, the default task duration unit is days, but you can change it to be minutes, hours, weeks, or months:

  1. Choose File > Options.

  2. In the Project Options dialog box, choose Schedule.

  3. Under Scheduling options for this project, in the Duration is entered in list, select a duration unit.

    Options dialog box, Scheduling options for this project area

  4. To use the same setting automatically in all future projects, select All New Projects in the Scheduling options for this project list.

See also

Change the default time unit for work

ต้องการความช่วยเหลือเพิ่มเติมหรือไม่

ต้องการตัวเลือกเพิ่มเติมหรือไม่

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.