Applies To„Project Online“ kompiuterio klientas „Project Professional 2024“ „Project Standard 2024“ Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016

The Assignment Delay fields show the amount of time a resource is to wait before starting work on an assignment. No information is actually displayed in the Assignment Delay task and resource fields; they merely make the corresponding Assignment Delay field information available.

There are several categories of Assignment Delay fields.

Data Type    Duration

Assignment Delay (task field)

Entry Type    Null

Best Uses    Add the Assignment Delay task field to the Task Usage view when you want to display delay information for assignments under a task.

Example    You are reviewing delay information for assignments. You add the Assignment Delay field to the Task Usage view. Although no information appears in the Assignment Delay field next to the task names, the delay for their assignments appears in the assignment rows below each task name.

Assignment Delay (resource field)

Entry Type    Null

Best Uses    Add the Assignment Delay resource field to the Resource Usage view when you want to display delay information for assignments under a resource.

Example    You are reviewing delay information for assignments. You add the Assignment Delay field to the Resource Usage view. No information appears in the Assignment Delay field next to the resource names. However, the delay for their assignments appears in the assignment rows below each resource name.

Assignment Delay (assignment field)

Entry Type    Calculated or entered

How Calculated    Microsoft Office Project calculates any difference between the assignment start date and the task start date. This difference is the assignment delay.

Assignment Delay = Start (task) - Start (assignment)

If you enter an assignment start date that is later than the task start date, the assignment delay field will change to reflect the difference between the assignment start date and the task start date.

Best Uses    To have an assignment start sometime after the start of the task, enter a value in the Assignment Delay field. Add the Assignment Delay field to the Task Usage or Resource Usage view when you want to review, filter, or edit the assignment delay.

Example    The "Conduct client meetings" task is assigned to Sean, Chris, and Jamie, with a duration of 5 days. However, Jamie is not to be involved with the task until the final day. To schedule Jamie for the final day of the task, type 4d in the Assignment Delay field (and 1d in the Work field) for Jamie's assignment.

Reikia daugiau pagalbos?

Norite daugiau parinkčių?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.