Data Type     Yes/No

Entry Type     Entered

Description     The Effort Driven field indicates whether the scheduling for the task is effort driven scheduling. When a task is effort driven, Project keeps the total task work at its current value, regardless of how many resources are assigned to the task. When new resources are assigned, remaining work is distributed to them.

Best Uses     Add the Effort Driven field to a task sheet when you want to set whether tasks are effort driven or resource driven directly on that sheet. If you want the same duration to be scheduled regardless of the number of resources assigned to the task, click No in the Effort Driven field. If you want the duration to be dependent on the availability and effort of the assigned resources, click Yes in this field.

Example     You have a task to create a set of architectural drawings with a duration of four weeks, which is how long the task would take one drafter to complete. Because the task is effort driven, you assign four drafters to the task and Project will schedule the task to be completed in one week. In this case, you click Yes in the Effort Driven field.

Later on, you schedule one week for client review of the drawings. Because you want one week scheduled regardless of how many clients review the drawings, you click No in the Effort Driven field.

Remarks     You can set whether a task is effort driven in the Task Information dialog box.

You can also set the default for all newly created tasks in the Project Options dialog box.

Perlu bantuan lainnya?

Ingin opsi lainnya?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.