Applies ToKlijent za računala za Project Online Project Standard 2024 Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016 Project Professional 2013 Project Standard 2013

Data Type     Currency

Entry Type     Entered

Description     For a work resource (people and equipment), the Cost Per Use field shows the cost that accrues each time a resource is used. It is added each time a work resource unit is assigned to a task. It does not vary with the amount of time you use the resource. For a material resource, the Cost Per Use field shows the cost that accrues at one time, regardless of the number of units.

Best Uses     Add the Cost Per Use field to a resource view to enter a cost for a work resource if the resource charges a set fee rather than (or in addition to) a variable, or hourly, fee. For a material resource, use this field to indicate a cost that's incurred once, regardless of the number of units.

Example     Every time you use a particular shuttle service, there is a fixed delivery charge of $10. You enter a cost-per-use value of $10. This charge is applied each time the service is used.

In the same project, there is a fixed storage fee of $350 associated with the use of bricks, a material resource. You enter the cost-per-use value of $350. This charge is only applied once.

Remarks     You can vary the cost per use across time. In the Cost rate tables in the Resource Information dialog box, you can enter a date and a new cost rate to begin on a particular date.

Potrebna vam je dodatna pomoć?

Želite dodatne mogućnosti?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.