Applies ToProject Online’i töölauaklient Project Standard 2024 Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016 Project Professional 2013 Project Standard 2013

Data Type    Currency Rate

Entry Type    Entered

Description    The Standard Rate field shows the rate of pay for regular, non-overtime work performed by a resource.

Best Uses    Add the Standard Rate field to a resource view to enter resources' rates of pay for regular work directly in the sheet. Whenever a resource reports actual work, the costs for the work are calculated by multiplying the actual work by the value in the Standard Rate field.

Example    Chris has a standard rate of $10 per hour. To make sure this cost is accurately calculated when Chris is used in your project, enter 10/h in the Standard Rate field. If you don't type a slash and time unit, the hours time unit is used.

Remarks    You can enter the standard rate for a resource in the Resource Information dialog box. You can also set a default standard rate in the Project Options dialog box. When a new resource is created, this default standard rate is set until you change it.

You can enter variable standard rates in the Resource Information dialog box. You can have different standard rates for different tasks using the multiple cost rate tables. This is helpful if the resource has different rates for different types of tasks. You can also specify different standard rates for different time periods. This is helpful when a resource is scheduled for a raise effective on a specific date. When you specify multiple variable rates, the rate displayed in the Rate field is for the current time period.

Kas vajate veel abi?

Kas soovite rohkem valikuvariante?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.