Applies ToProject Online’i töölauaklient Project Professional 2021 Project Standard 2021 Project Professional 2019 Project Standard 2019 Project Professional 2016 Project Standard 2016 Project Professional 2013 Project Standard 2013

The Post Implementation Review Notes field stores review meeting notes or a link to a meeting notes publication for the post-implementation review. This field is controlled by the workflow.

Data Type    Text

Entry Type    Entered

Best Uses    Post-implementation review is the last of 14 suggested workflow stages. The review can be a lessons-learned or “post-mortem” meeting with project team members, or it can be an individual assessment of the project by the project manager. Add the Post Implementation Review Notes field to a proposal when you want to include the notes for the post-implementation review meeting as part of a project proposal. This provides useful information for the Portfolio Analysis process.

Example    You are proposing a project to develop a Web-based customer service solution. You add the Post Implementation Review Notes field to the proposal and enter the preliminary agenda you have developed for the post-implementation review meeting.

Remarks     This field is an example of a custom multiline text field provided with Microsoft Project Server. You can view a list of available custom fields, and also create your own. In the left pane of Microsoft Project Web Access, click Server Settings. Under Enterprise Data, click Enterprise Custom Fields and Lookup Tables.

Kas vajate veel abi?

Kas soovite rohkem valikuvariante?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.