Data Type    Duration

Entry Type    Calculated

Description    The Free Slack field contains the amount of time that a task can be delayed without delaying any successor tasks. If the task has no successors, free slack is the amount of time that a task can be delayed without delaying the entire project's finish date.

How Calculated    If the task has no successor tasks, free slack is the same as total slack. Microsoft Office Project bases its calculations of free slack on comparisons of the dates in the Early Start, Early Finish, Late Start, and Late Finish fields for the task, which in turn take into account the dates for any successor tasks.

Best Uses    Use the Free Slack field to determine whether a task has any time available for a delay. This can be useful if a resource needs more time on a task, or if you want to assign a resource to another task. You can also use the Free Slack field to determine how to recover a schedule that's slipping.

Example    You are reviewing the schedule and want to see if there is any free slack on tasks. You add the Free Slack field to the Task Sheet view to see if a delay on tasks with free slack will affect any other tasks.

Kas vajate veel abi?

Kas soovite rohkem valikuvariante?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.