Data Type    Duration

Entry Type    Calculated

Description    The Finish Slack field contains the duration between the Early Finish and Late Finish dates. The smaller of the finish slack and start slack amounts determines the amount of free slack available, that is, the amount of time a task can be delayed without affecting the start date of a successor task or the project finish date.

How Calculated    Finish slack is the duration that represents the difference between the late finish and early finish dates. The early finish is the earliest date that a task could possibly finish. Likewise, the late finish field contains the latest date that a task can finish without delaying the finish of the project. Project calculates the finish slack as follows:

Finish Slack = Late Finish - Early Finish

Best Uses    Add the Start Slack and Finish Slack fields to any task view when you want to review how free slack was calculated.

Example    You are reviewing free slack in your schedule and want to see more details about how it was calculated. You add the Start Slack and Finish Slack fields to the task sheet and analyze the durations.

Remarks    If a task has an actual start date and also a deadline set, the start slack will be 0 and the finish slack will be the difference between the task's finish date and deadline date.

Kas vajate veel abi?

Kas soovite rohkem valikuvariante?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.